Phase 1-Burgi Lane Water Line Replacement Project
UPDATE February 3, 2026
Phase one of the Burgi Lane Water Line Replacement Project is nearing completion. Beginning on Wednesday, February 4th, the traffic signals will be removed, and 4-way flagging will be set at the intersection of Burgi Lane and Interlaken Dr. Please drive carefully and follow the posted road signs and traffic flaggers. Phase two will begin on Thursday, February 5th. The traffic signals will be relocated to the west side of Center St. The project will then continue west towards Pine Canyon Dr.
Please contact the City Offices with any questions. 435-654-3223
or email tsmout@midwaycityut.gov